New Construction

New Construction Residential and Commercial Developement

We require 3 copies of the preliminary drawings of the water mains, fire service mains and fire sprinkler mains for the developement.

After water main drawings are approved by Public Water Supply Dist. # 1, we will require 3 copies of approved drawings.

The Devloper/Contractor will enter into a contract with Public Water Supply Dist. # 1 for the construction of water mains and submit a Certificate of Insurance.

The Developer/Contractor will be required to obtain a copy of Ord. 6301 Specifications and Details for Water Main Construction from Public Water Supply Dist. # 1.

The Developer/Contractor will be required to put down a deposit for construction with Public Water Supply Dist. # 1. The deposit for construction is to cover all inspection fees, water and labor used for flushing, pressure testing and Bac-T sampling.

The Developer/Contractor will schedule a pre-construction meeting at our office with Public Water Supply Dist. # 1 and our inspector for the project.

All requirements must be met before construction of the water mains can begin.

 

Schedule of Deposit Based on Water Main Footage

 1-100 feet   $35.00/ft. 
 101-500 feet  $25.00/ft.
 501-1,000 feet  $10.00/ft.
 1,001-2,000 feet  $6.30/ft.
 2,001-4,000 feet   $3.25/ft.
 4,001-6,000 feet    $2.50/ft.
 6,001 -10,000 feet  $2.00/ft.

  

Ord. 6301 Standard Specifications

$15.00 per copy

 

New Meter Service Installation

3/4"-6" Typical Installation

Meter Pit Installation Charges

Meter Size  Tap Size  Meter  Tap  Total Cost

 

 5/8"x3/4"     3/4"  $600.00  $300.00  $900.00

no refund

     1"      1"  $800.00  $300.00  $1,100.00

no refund

    1.5"      2"  $1,400.00  $300.00  $1,700.00

actual cost 

     2"      2"  $1,600.00  $300.00  $1,900.00

actual cost 

     3"      3"  $2,500.00  $300.00  $2,800.00

actual cost 

     4"      4"  $3,500.00  $300.00  $3,800.00

actual cost 

     6"      6"  $7,000.00  $300.00  $7,300.00

actual cost